"Because of them, I'm selling my car": gas workers can't wait for their salaries, and Chita residents can't wait for gasification.
In Chita, 4872 homes cannot be connected to gas under the Clean Air program of the Ecology national project because employees of the Moscow-based Vershina company have not received their salaries since May.
"I started working there in mid-April. Everything was great at first. Then there were delays—the advance, then the salary. For May, June, and the beginning of July, I only received 30 rubles. Now, because of them, I'm selling my car to pay off my credit card," one of Vershina's former employees told NeMoskva.
The company promised to explore its own funds to pay off the debt after coordinating all issues with the Ministry of Housing and Public Utilities.
Vershina signed a contract for these works at the end of 2024. How explained At the company, salary problems arose due to lengthy approval processes with the regional Ministry of Housing and Public Utilities and an inspection by the prosecutor's office.
Chita's gasification system has been facing problems for several years. Under the Clean Air program, the city was supposed to be connected to gas by the end of 2024, but the deadline was pushed back to September 2025. In an interview, a Vershina representative promised complete all work by the end of the year.
The prosecutor's office has repeatedly found Violations at gasification facilities: schedule delays, lack of funding, and missed expert assessment deadlines. Gas storage facility in Chita not built not at all, wrote Chita.ru.
The head of the previous contractor company, Stanislav Novikov арестовали in May 2024. He was accused of embezzling more than 877 million rubles and sentenced to 3,5 years in a general regime penal colony.
Photo: The Transbaikal Prosecutor's Office conducts an inspection at a gasification facility.